answer question a correctly, and show sample calculation/formula used A manufacturer has set up a project for developing a new machine for one of its
answer question a correctly, and show sample calculation/formula used A manufacturer has set up a project for developing a new machine for one of its production
lines. The engineering department has provided a project proposal that estimates the following
investment requirements: I )An initial investment of 300,000$ to be paid for purchasing the new machine. iij An additional cost is needed to install the machines and integrate it into the overall
production system and it is estimated to take one (1) year for completion. There are three
cost categories involved: . Engineering labour cost, estimated to be 1200 hours at a cost of 100$lhour. – None—engineering labour cost estimated to be 3000 hours at a cost of 50$fhour. – Assorted material cost, estimated to be 100100035. iv) The machine has to be overhauled every 2 year, and it costs 2010003; beginning in the
third year of the project. They will not overhaul the machine in the last year of its life. v} The production will be started in the second year, and it will be up—to—sp-eed by the end
of that year. vi} Projected manufacturing cost savings and added profits are estimated to be 100,000$
in the first year of operation and are expected to peak at 250,000$ in the third year of
operation and then to follow the gradually declining pattern shown in Table 1. vii) Project life is expected to be 8 years. viii) It is estimated that the machinery will have a salvage value of 50,000$ at the end of
the operation. Table 1. Cost saving and added profits of project
Year of production
Profit ($)
100,000
230,000
250,000
243,000
227,000
a) If the company has a 10 percent hurdle rate for capital investment, estimate the Net
Present Value (NPV) of the project.
(10 marks)
b) would happen to the NPV of the above project, if the inflation rate was expected
to be 1.5% per year? Comment on the project whether to be accepted or rejected.
(10 marks)

How it Works

1
It only takes a couple of minutes to fill in your details, select the type of paper you need (essay, term paper, etc.), give us all necessary information regarding your assignment.


2
Once we receive your request, one of our customer support representatives will contact you within 24 hours with more specific information about how much it'll cost for this particular project.


3
After receiving payment confirmation via PayPal or credit card – we begin working on your detailed outline, which is based on the requirements given by yourself upon ordering.


4
Once approved, your order is complete and will be emailed directly to the email address provided before payment was made!